Change Order

Scope changed mid-project — document it, get it signed, protect your margin.

Not legal advice. This is a starting point. Review with a lawyer before signing anything that matters.

What a change order actually does

A change order records work added after the contract was signed: what changed, what it costs, and what it does to the timeline. Signed, it turns scope creep into a line item. Unsigned, it is an argument waiting to happen at final invoice.

When you need one

  • Any request that was not in the original scope, however small it sounds.
  • Before doing the extra work, which is the only time the conversation is easy.
  • Including when the change costs nothing, so the record shows what was agreed and why.

What it should contain

The original agreement
Referenced by name and date.
What is changing
Specifically. "More social cuts" is not a scope; "four additional 15-second vertical cuts" is.
The cost
What the change adds, and whether it is payable now or at final invoice.
The effect on the schedule
Extra work usually moves delivery. Say by how much, now.
Signatures
From whoever can authorise spending, not just your day-to-day contact.

What people get wrong

Doing the work first and raising it later
Once it is delivered, you are asking for a favour rather than agreeing a price.
Not adjusting the deadline
Accepting extra work while holding the original delivery date is how a project ends badly.
Getting it signed by the wrong person
The contact who asked may have no authority to commit budget. Find out who does.
Skipping it for small changes
Five small unrecorded changes become an invoice the client does not recognise.

Common questions

When is a change order needed rather than just saying yes?
Whenever the request falls outside what the contract described, or affects the delivery date. The test is not size — it is whether the original agreement covered it.
What if the client refuses to sign one?
Then the change is not agreed, and the original scope stands. That is uncomfortable to say and much less uncomfortable than doing unpaid work and discovering it at final invoice.

Make scope creep a line item

Added work goes onto the job and onto the invoice, so it is billed rather than argued about three months later.